Shotcreting of the eaves continues. They applied the first coat of the cementitious powermix, Bostik, after all the cracks have been sealed with Polytuf. The mason is finishing the edge of the roof. Once that is done his job will be done. The remaining workers will be the ones to finish waterproofing and painting the roof.
We had a visitor for the past 4 days so we were not able to keep an eye on the work, but, thankfully, there is continued progress every time we come home at the end of the day.