Days 10 & 11

(Update on my tablet: It got totally discharged when the lady at the store reset it. Hopefully, it was just a battery problem. Otherwise, we will have to bring it to the service center in the city. :/  Tried to upload pictures using this tablet, not mine, but it took forever. Will post them once I get to charge my tablet.)

Anyway, on Saturday we were able to completely finish 9 panels, cleared 3  panels, and applied cement on almost all 3. One of our worker was absent then so only DH and the other worker set up the scaffolding so they can reach the panel that is above our bedroom closet. That took most of the first half of the day. At least by the 2nd half they managed to cement most of the panels.

Next week, on Monday in particular, we want to completely finish those 3 panels. On Tuesday, one of the workers will be taking half the day off. So we hope to set up the scaffolding by the bathroom before he leaves for the day. We will have to figure this out as the scaffolding is too big to be placed inside the bathroom. Then they can proceed with the removal of the mat/plastic/net/tarp.

We hope we can stick to this schedule so we will be able to complete the project by mid-June.

No comments:

Post a Comment