Saturday, May 9, 2015

Inside roof work soon to begin

On saturday we have begun setting up our scaffolding inside the house. We plan to work 2 panels at a time as we only have 2 workers and a small space to move around. We will most likely being removing the plastic sheeting and tarp on Tuesday. Instead of doing shotcrete, we will just use pure cement mix and paste it smooth in areas where there are exposed wire mesh. Then paint on the cementitious waterproofer followed by paint.

We were thinking of doing this next year but we realized we needed to make sure these exposed wire mesh will not completely rust, especially when the rainy season is almost upon us - the humidity will surely contribute to it. it is better we do this now.